| Veterans Administration Hospital |
| Location: |
Scope of Contract: |
| Fort Snelling, Minnesota |
Install interior drywall partitions, spray on fireproofing, lath and plaster, and lead-lined x-ray partitions. |
| General Contractor: |
Contract Size: |
| M. A. Mortenson/Barton Malow |
$7,200,000 |
| Description of Project: |
Major Challenge: |
| New 1,500,000 square feet hospital |
Install fire rated partitions in confined interstitial space, build high STC (sound) ratings into partitions, maintain consistent performance throughout duration of project. |
| |
| click picture for larger view, close picture window by clicking X |
|
|
|
|
|
|